Add Material on the Material Costs Panel
Add employee or contractor material on the Material Costs panel in ELM.
|
|
NOTE: All images were taken from a work order. While there are differences between the work activities, the functionality and the steps are the same.
- Open ELM. See Open ELM for more information.
- On the Material Costs panel, select Actual to add confirmed costs or select Estimated to add anticipated costs.
- Click Add record in the Standard or Contractor section.
- Add the cost information, all required fields are marked in red. Assets can be added to a cost on the cost panel. See Add Material on the Material Costs Panel for more information.
NOTE: When adding labor, equipment, and material provided by a contractor, enter the total cost in the Cost field. The system does not calculate the cost by the number of Hours and/or Units entered.
- Click Save.
The new material costs show in the Cost Summary and the Material Costs panels.
IMPORTANT: Information entered in the Cost field must be the total cost of all units. Trimble Unity does not calculate the cost of the units.